Question #: 32
Topic #: 4

Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?


A.

Try to secure formal agreement as to how many hours per week the

marketing assistants will spend on the project.


B.

Accept that members of the Solution Development Team will be

inconsistent.


C.

Make each Timebox as long as possible to ensure the marketing

assistants have enough time to complete any work allocated to them

within the boundaries of the Timebox.


D.

Schedule the two marketing assistants to work at different times so they

can hand matters over to one another.