Question #: 5
Topic #: 1

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?


A.

Refuse to discuss any detailed requirements in the early phases.


B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.


C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.


D.

Capture the Marketing Director ' s requirements in detail but leave the

input of others until later in the project.