AgilePM-Foundation Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

According to Tuckman, in what stage of the team development model can everyone move on to new things, feeling good about what has been achieved?


A.

Forming.


B.

Storming.


C.

Performing.


D.

Adjourning.