How does the Post-Project phase add value to a project?


A.

Define how the operation of the solution will be managed


B.

Iteratively explores the low- level detail of the requirements


C.

Checks how well the expected business benefits have been met


D.

Brigs a baseline of the Evolving Solution into operational use