APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 77 Topic 7 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 77 Topic 7 Discussion

APM-PFQ Exam Topic 7 Question 77 Discussion:
Question #: 77
Topic #: 7

Which of these statements is FALSE?


A.

Stakeholders may be for the change or against


B.

Stakeholders may have little influence or lots


C.

Stakeholders may be internal or external to your organisation


D.

Stakeholders with high influence always have high interest in the project