APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 21 Topic 2 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 21 Topic 2 Discussion

APM-PFQ Exam Topic 2 Question 21 Discussion:
Question #: 21
Topic #: 2

By carrying out a stakeholder analysis, project managers can assess whether or not stakeholders are:


A.

making unfair judgements.


B.

able to bring expertise to the project team.


C.

in a position to affect their careers.


D.

for or against the project outcomes.