Question #: 119
Topic #: 11

One aspect of quality planning is to:


A.

plan the audit of a project to provide assurance to the project board.


B.

provide confidence that a project will achieve its objectives in the required time frame.


C.

specify the acceptance criteria used to validate the outputs are fit for purpose.


D.

confirm routes for reporting to ensure effective communication