On examining a particular risk in the project there is some uncertainty among the project team of how important this risk is to the project. How would you advise the team on how the significance of the risk is to be determined?


A.

By assessing its probability of occurrence.


B.

By assessing its impact on project objectives,


C.

By assessing both its probability of occurrence and its impact on project objectives.


D.

By assessing its effect on the business case.