APM-PFQ Exam Topic 11 Question 113 Discussion:
Question #: 113
Topic #: 11

The document that identifies what information needs to be shared, to whom, why, when and how is called the:


A.

communication management plan.


B.

stakeholder mapping grid.


C.

document distribution schedule.


D.

responsibility assignment matrix.