Question #: 105
Topic #: 10

Which of the following would not be considered as part of the post project review?


A.

Evaluation of the benefits of the project.


B.

Identification of the problems that arose and their likely causes.


C.

Review of the project's performance against the success criteria.


D.

Review of how the team worked together to solve problems and issues.