APICS Certified in Transformation for Supply Chain (CTSC) CTSC Question # 35 Topic 4 Discussion
CTSC Exam Topic 4 Question 35 Discussion:
Question #: 35
Topic #: 4
A production line has a total of 8 hours of line time available. If it takes 2 hours to prepare the line to run the product and 5 hours of actual run time, what is the utilization rate?
Chosen Answer: