Question #: 35
Topic #: 4

A production line has a total of 8 hours of line time available. If it takes 2 hours to prepare the line to run the product and 5 hours of actual run time, what is the utilization rate?


A.

87.5%


B.

62.5%


C.

50.0%


D.

37.5%