CPIM-8.0 Exam Topic 15 Question 145 Discussion:
Question #: 145
Topic #: 15

The project manager has updated the project steering committee that a security vulnerability was found after applying the system security baseline, and remediation has been completed to close the vulnerability. What is the BEST next step for the project?


A.

Update the security baseline and continue with the next project task.


B.

Proceed with the next project task to meet the project deadlines.


C.

Obtain approval from the project steering, committee to revise the system security baseline.


D.

Create a change request for the system baseline revision.