An effective approach to projecting requirements for materials with long lead times is to initiate a multilevel master schedule. A multilevel master schedule is a detailed plan that shows the quantities and timing of the end items and all of their components at each level of the bill of materials (BOM). By using a multilevel master schedule, a planner can determine the requirements for materials with long lead times and place orders in advance to avoid shortages or delays. A phantom bill of materials (BOM) is a temporary grouping of components that are used in the production of a parent item, but do not exist as a separate item in inventory. A phantom BOM is not an effective approach to projecting requirements for materials with long lead times, as it does not reflect the actual demand for the components. Increasing the level of safety stock is a way of mitigating the risk of uncertainty in demand or supply, but it is not an effective approach to projecting requirements for materials with long lead times, as it increases the inventory carrying costs and does not address the root cause of the problem. Decreasing the planning horizon is the opposite of an effective approach to projecting requirements for materials with long lead times, as it reduces the visibility and accuracy of the forecast and increases the likelihood of stockouts or excess inventory. References:
CPIM Part 2 Learning System, Module 3: Supply, Section 3.2: Material Requirements Planning
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit