The consequence analysis in an RBI program is performed to:


A.

discriminate between equipment items on the basis of the significance of a potential failure.


B.

establish on the basis of consequence a prioritized ranking of equipment items for RBI plans.


C.

establish on the basis of consequence a relative risk ranking of equipment subject to failure.


D.

provide management with numerous options for limiting the consequence of a potential failure.