Question #: 41
Topic #: 5

A lien act requires tie owner of land or a building under construction to:


A.

pay liens only to workers or suppliers with whom the owner has a contract.


B.

hold back the payment for construction until the Job is completed.


C.

pay Mans automatically if the Man claim is filed within the legal limitation period.


D.

hold back a specified percentage of construction costs to pay possible claims.