In controlling the master schedule, which of the following activity is NOT included?
Track actual production and compare it to the planned production
Calculate the available-to-promise to determine if an incoming order can be promised
Determine the rough-cut capacity requirements plan
Use results of preceding activities to determine if capacity should be revised