After a system goes live, continuous monitoring is needed for:
Benefit plan integration (A)
Tax legislation changes (B)
Evolving reporting requirements (C)
However, parallel testing is done before go-live to compare old and new system outputs for accuracy. Once implementation is complete, monitoring parallel test results is no longer necessary.
✅ Correct answer: D – Parallel test results
[References:, APA Payroll Source – System Implementation and Testing, APA Implementation Lifecycle Documentation, ]
Contribute your Thoughts: