Amazon Web Services Amazon AWS Certified Advanced Networking - Specialty ANS-C01 Question # 38 Topic 4 Discussion

Amazon Web Services Amazon AWS Certified Advanced Networking - Specialty ANS-C01 Question # 38 Topic 4 Discussion

ANS-C01 Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

A company is migrating applications from a data center to AWS. Many of the applications will need to exchange data with the company's on-premises mainframe.

The company needs to achieve 4 Gbps transfer speeds to meet peak traffic demands. A network engineer must design a highly available solution that maximizes resiliency. The solution must be able to withstand the loss of circuits or routers.

Which solution will meet these requirements?


A.

Order four 10 Gbps AWS Direct Connect connections that are evenly spread over two locations. Terminate one connection from each Direct Connect location to a router at the company location. Terminate the other connection from each Direct Connect location to a different router at the company location.


B.

Order two 10 Gbps AWS Direct Connect connections that are evenly spread over two locations. Terminate the connection from each Direct Connect location to a different router at the company location.


C.

Order four 1 Gbps AWS Direct Connect connections that are evenly spread over two locations. Terminate one connection from each Direct Connect location to a router at the company location. Terminate the other connection from each Direct Connect location to a different router at the company location.


D.

Order two 1 Gbps AWS Direct Connect connections that are evenly spread over two locations. Terminate the connection from each Direct Connect location to a different router at the company location.


Get Premium ANS-C01 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.