CHFM Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

The annual utility bill at a hospital is $1.2M for a 500,000 sq. ft. facility. The current construction project will add 100,000 sq. ft. to the facility. What is the anticipated annual utility budget after the construction project is completed?


A.

$240,000


B.

$1,440,000


C.

$1,728,000


D.

$1,828,000