AEE Certified Energy Manager (CEM) CEM Question # 18 Topic 2 Discussion
CEM Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2
Which of the following is NOT a typical benefit of performance contracting from the building owner's perspective?
A.
Performance contracting is a simple and quick process
B.
Net cash flow can be neutral or positive for the owner
C.
The energy-service company can have a financial incentive to achieve projected savings
D.
Maintenance services provided by the performance contractor can add value to the overall savings achieved
E.
Performance contracting can provide access to external financing when the owner may not have sufficient equity for in-house financing for large projects
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit