CEM Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

You are using a performance contract to finance the added cost of using more-efficient equipment in the construction of a new building. Which of the following International Performance Measurement and Verification Protocol (IPMVP) options would you use to verify annual energy savings?


A.

Option A - Retrofit isolation: key parameter measurement


B.

Option B - Retrofit isolation: all parameter measurement


C.

Option C - Whole facility measurement


D.

Option D - Calibrated simulation


E.

Option E - Stipulated savings