In Adobe Workfront, when a project is set to " In Progress, " the default project condition is marked as " On Target. " This reflects that the project is actively being worked on and progressing as expected without any significant issues or delays. The " On Target " condition is designed to signal that the project is meeting the planned timelines and performance metrics.
The New and Idea statuses are preliminary stages where active progress or development has not started yet, and thus these statuses would not set the project condition to " On Target. " Instead, they may represent an early phase of consideration or planning, where progress and targets have not been set in motion.
This is an essential feature within Workfront for project management, allowing teams to understand at a glance whether a project is moving as planned or if it requires attention based on predefined thresholds for performance or timing.
For further detailed information, please refer to the Adobe Workfront documentation on project statuses and conditions, which elaborates on how different statuses affect project tracking and reporting.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit