Detailed Explanation:
Ensure late bids are accepted,
Extend deadlines unfairly,
Or falsify bid logs.Bid-splitting, however, is a scheme performed to avoid approval thresholds and does not require bribery of purchasing employees.
Analysis of Incorrect Options:
A. Receipt of late bid – Real reason to bribe.
B. Extend opening date – Real reason to bribe.
D. Falsify bid log – Real reason to bribe.
C. Ensure bid-splitting – Not a bribery motivation.
Key Concept:Bribery motivations in procurement fraud.
[Reference:ACFE Fraud Examiners Manual (2020 International Edition), Corruption — Bribery Schemes in Procurement., , ]