Questions # 31:

A refrigerant-to-water heat exchanger can be added to air-conditioning equipment to heat water using the waste heat in the vapor compression refrigerant cycle. Where is this type of heat exchanger located in the refrigerant loop?

Options:

A.

After the condenser coil, before the thermal expansion valve


B.

After the expansion valve, before the evaporator coil


C.

After the evaporator coil, before the compressor


D.

After the compressor, before the condenser coil


Expert Solution
Questions # 32:

In general, which of the following is the least expensive and easiest way to finance an energy project?

Options:

A.

Equity


B.

Debt


C.

Performance contract


Expert Solution
Questions # 33:

What is a common method to reduce the impact of voltage imbalance?

Options:

A.

Rebalance single-phase loads


B.

Install harmonic filters


C.

Install capacitors to improve power factor on three-phase loads


D.

Reverse phase connections on three-phase motors


Expert Solution
Questions # 34:

How can commissioning reduce the life-cycle cost to owners and operators?

Options:

A.

Reduce the cost of change orders during construction


B.

Improve the performance of energy systems


C.

Improve the satisfaction of building occupants


D.

Improve the effectiveness of operations and maintenance


E.

All of the above


Expert Solution
Questions # 35:

At the end of a performance contract, who owns the equipment installed by the project?

Options:

A.

The bank


B.

The energy service company


C.

The equipment manufacturer


D.

The company that paid the contract payments


Expert Solution
Questions # 36:

You can buy air compressor A for $15,000 or air compressor B for $6,000. Compressor A will cost $10,000 per year to operate. Compressor B will cost $11,500 per year to operate. If both air compressors have a 10-year life and your required return on investment is 12%, which air compressor has the lowest total life-cycle cost?

Options:

A.

Compressor A


B.

Compressor B


C.

Both air compressors have the same life-cycle cost


Expert Solution
Questions # 37:

Which of the following instruments is most useful for tracking long-term boiler performance?

Options:

A.

The pressure gauge


B.

The exhaust stack temperature sensor


C.

The boiler room ambient temperature sensor


D.

The drum water level gauge


E.

The feedwater temperature sensor


Expert Solution
Questions # 38:

In an ammonia-water absorption chiller, what material is the refrigerant?

Options:

A.

Some form of fluorocarbon


B.

Water


C.

Lithium bromide


D.

Ammonia


Expert Solution
Questions # 39:

A new energy-efficient boiler costs $60,890 to buy and install. The new energy-efficient boiler will save $15,400 per year and last for 20 years. What is the internal rate of return (IRR) of the project?

Options:

A.

10%


B.

15%


C.

20%


D.

25%


E.

30%


Expert Solution