Workday calculated fields allow users to manipulate dates, numbers, and text values. To calculate a new date based on an existing date field (e.g., Bonus Approval Date), you use theIncrement or Decrement Datefunction. This adds or subtracts a defined number of days, months, or years from the source date.
From Workday Reporting documentation:
“Increment or Decrement Date – Returns a date that is a specified number of days, months, or years before or after the value of the source date field.”
Example: If the Bonus Approval Date is 01/01/2025, adding 60 days using this function would return 03/02/2025.
Thus, the correct choice isA. Increment or Decrement Date.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.