Question #: 20
Topic #: 3

Please read this scenario prior to answering the question

You are employed as an Enterprise Architect consultant within a manufacturing company. The company hasmultiple business units located worldwide, including retail, manufacturing, pharmaceuticals, and technology.

The company has a mature Enterprise Architecture (EA) practice and uses the TOGAF standard for itsarchitecture development method. The EA practice is engaged throughout all the business units, withgovernance provided by multiple Architecture Boards with responsibility for a business line. In addition to theEA program, the company uses a number of management frameworks, including business planning,project/portfolio management, and operations management. The EA program is sponsored by the ChiefInformation Officer (CIO).

After a recent study, senior management are concerned about the impact of the company's multiple datacenters and duplication of applications on the business efficiency. To address the concern, a strategicarchitecture has been defined; it will help improve the ability to meet customer demand and improve theefficiency of operations. The strategic architecture involves the consolidation of multiple applicationsprograms that are currently used in different business units and putting them all onto a cloud-based solutioninstead.

Each business unit has completed the Architecture Definition documentation to meet its own specificoperational requirements. The Enterprise Architects have analyzed the corporate changes andimplementation constraints. A consolidated gap analysis has been completed. Based on its results, thearchitects have reviewed the requirements, dependencies and interoperability requirements needed tointegrate the cloud-based solution. The architects have completed the Business Transformation ReadinessAssessment. Based on all these factors they have produced a risk assessment. They have also completedthe draft Implementation and Migration Plan, the draft Architecture Roadmap, and the CapabilityAssessment deliverables.

Due to the risks of changing from the current environment, the decision has been taken that a gradualapproach is needed to implement the target architectures. It will likely take a few years to complete thewhole implementation process.

Refer to the scenario

You have been asked to decide on the next steps for the migration planning.

Based on the TOGAF standard which of the following is the best answer?


A.

You update the Architecture Definition Document, which includes setting project objectives and

documenting the final requirements. This will ensure that the architecture remains relevant and

responsive to the needs of the enterprise. You then produce an Implementation Governance Model to

manage the lessons learned prior to finalizing the Implementation and Migration plan. You

recommend that lessons learned be quickly


B.

You estimate the business value for each project by applying the Business Value Assessment

Technique. The assessment should focus on return on investment and performance evaluation

criteria used to monitor the progress of the architecture transformation. You confirm and plan a series

of Transition Architecture phases using an Architecture Definition Increments Table. You then

document the lessons learned and generate


C.

You need to determine how the Implementation and Migration plan fits with the other frameworks

being used in the organization. You coordinate the planning with the business planning,

project/portfolio management and operations management frameworks. You assign a business value

to each project, considering the available resources and how well they align with the strategy. You

then update the architecture roadmap and t


D.

You conduct a Compliance Assessment to ensure that the architecture is being implemented

according to the contract. The Compliance Assessment verifies that the implementation team is using

the proper development methodology. It should also include deployment of monitoring tools. If the

monitoring tools show that performance targets are not being met, then the performance

requirements should be changed and the Impleme