New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Scrum SAFe Practitioner Exam (6.0) SAFe-Practitioner Question # 62 Topic 7 Discussion

Scrum SAFe Practitioner Exam (6.0) SAFe-Practitioner Question # 62 Topic 7 Discussion

SAFe-Practitioner Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

A team finishes developing all of their Stories in the first six days of the Iteration, tests them in the following two days, and fixes bugs in the days remaining. How is the team behaving?


A.

They are abusing the practice of hardening


B.

They are ignoring nonfunctional requirements within the Iteration


C.

They are waterfalling the Iteration


D.

They are applying the Agile development practice of "separation of concerns"


Get Premium SAFe-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.