On day two of PI Planning, management presents adjustments based on the previous day's management review and problem-solving meeting. What is one possible type of adjustment they could make?
On day two of PI Planning, management presents adjustments based on the previous day’s management review and problem-solving meeting. The management review and problem-solving meeting is a session where the management team reviews the draft plans and objectives from the teams, identifies risks and dependencies, and resolves any issues that may affect the ART’s ability to deliver value. One possible type of adjustment they could make is to adjust the business priorities based on the new information and feedback from the teams. This could involve reprioritizing the features in the program backlog, changing the weight or value of some objectives, or adding or removing some stretch objectives. These adjustments are communicated to the teams during the second planning day, so they can finalize their plans and objectives accordingly. References: PI Planning - Scaled Agile Framework, PI Planning and the Management Review - Part 1 | Ivar Jacobson International
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit