Scrum Professional Scrum Master I PSM-I Question # 37 Topic 4 Discussion

Scrum Professional Scrum Master I PSM-I Question # 37 Topic 4 Discussion

PSM-I Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)


A.

The Scrum Masters from each Scrum Team define a common Definition of Done.


B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.


C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.


D.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.