Scaled Agile SAFe for Teams SP (6.0) - SAFe Practitioner SP-SAFe-Practitioner Question # 42 Topic 5 Discussion

Scaled Agile SAFe for Teams SP (6.0) - SAFe Practitioner SP-SAFe-Practitioner Question # 42 Topic 5 Discussion

SP-SAFe-Practitioner Exam Topic 5 Question 42 Discussion:
Question #: 42
Topic #: 5

During the PI Planning event, when are planning adjustments agreed upon?


A.

During breakout sessions


B.

During the draft plan review


C.

During the Coach sync


D.

During the management review and problem-solving meeting


Get Premium SP-SAFe-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.