You are running an indirect activity allocation. What do you post to the sender and receiver?
You post only cost to both the sender and receiver.
You post quantity and cost to both the sender and receiver.
You post both quantity and cost to the sender, and cost only to the receiver.
You post both quantity and cost to the receiver, and cost only to the sender.
Submit