SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 14 Topic 2 Discussion
C_TS412_2021 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2
You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question
To determine the planned costs for an internally processed activity, you need the duration and activity type data. The duration is the time required to complete the activity. The activity type is a classification of activities according to their functions or characteristics. The system calculates the planned costs for an internally processed activity based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit