The various work packages in the project are described as individual activities. Activities are the smallest units of a project that can be planned, executed, and controlled. Activities can be assigned to one or more WBS elements in a project. Activities can also be linked to each other by relationships to define the sequence and dependencies of the work packages. Reference:https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html