SAP Certified Application Associate - SAP S/4HANA Project Systems C_TS412_2021 Question # 7 Topic 1 Discussion
C_TS412_2021 Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
A.
Enter an offset of -18 days to the finish date of the activity
B.
Enter February 10 as fixed date
C.
Enter 10 days as duration
D.
Enter an offset of 10 days to the start date of the activity
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference:https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html