SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management C_S4PPM_1909 Question # 4 Topic 1 Discussion

SAP Certified Application Associate - SAP S/4HANA Portfolio and Project Management C_S4PPM_1909 Question # 4 Topic 1 Discussion

C_S4PPM_1909 Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

What must you configure to view portfolio item data in project management projects?


A.

Set the project management flag to active in customizing for the linking item type


B.

Set the business content data source for portfolio management in customizing


C.

Set the objects link flag to active in customizing for the project management structure


D.

Set the portfolio management flag to active in customizing for the project type