C_OCM_2503 Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

A repeated stakeholder analysis for the management team of an impacted business unit reveals that targeted communication activities for one opponent do not have the desired impact on the opponent’s attitude. What would you recommend as a next activity?


A.

Use financial incentives to motivate the opponent to visibly support the project and thus foster the opponent’s buy-in.


B.

Invite the opponent to the next steering committee meeting to discuss and challenge their negative perception of the project.


C.

Ask the project sponsor to get actively involved in stakeholder engagement activities targeted at the opponent.


D.

Provide specific enablement sessions to positively influence the opponent’s attitude.