The stakeholder analysis in a cloud project reveals that some individual stakeholders belong to the “supporters” category. Which strategies should you use? Note: There are 2 correct answers to this question.
A.
Ask them to exert pressure on the skeptics in their area of responsibility
B.
Involve them in project activities to facilitate design decisions
C.
Assign them project roles to increase their influence on the success of the project
D.
Use their positive attitude to influence others in their area of responsibility