C_ARSOR_2404 Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

In a multistage event, what is the purpose of running an RFI before conducting an RFP or an auction? Note: There are 2 correct answers to this question.


A.

To narrow the list of suppliers to invite to later events


B.

To gather pricing and capability information


C.

To gain a preliminary bid from each supplier


D.

To verify if suppliers can meet the specifications