Question #: 6
Topic #: 1
In a multistage event, what is the purpose of running an RFI before conducting an RFP or an auction? Note: There are 2 correct answers to this question.
A.
To narrow the list of suppliers to invite to later events
B.
To gather pricing and capability information
C.
To gain a preliminary bid from each supplier
D.
To verify if suppliers can meet the specifications
Chosen Answer: