After the schedule line is released and communicated to the supplier in the Supplier Managed Inventory (SMI) process, theFirmed Order (C)key figure is updated on the SMI detail screen. This key figure represents the confirmed quantity that the supplier is committed to delivering, reflecting the firmed demand in the supply chain planning process.
The other key figures—In-transit (A),ASN Received (B), andGoods Received (D)—are updated at different stages of the procurement and fulfillment process:
In-transit (A): Updated when goods are en route to the buyer.
ASN Received (B): Updated upon receipt of the Advance Ship Notice from the supplier.
Goods Received (D): Updated when the goods are physically received and recorded in the system.