In SAP Business Network Supply Chain Collaboration, forecast data from the ERP system can originate from various sources. Among the options provided, the correct sources are:
A. Planned order: Planned orders represent anticipated production or procurement activities and serve as a basis for forecasting demand.
D. Planned independent requirement: These are forecasts of demand for finished products or components, independent of actual sales orders, and are crucial for planning purposes.
The other options are not considered sources of forecast data:
B. Production Order: This is an actual order to produce a specific quantity of a product and reflects confirmed production activities rather than forecasted data.
C. Purchase requisition: This is a request for the procurement of materials or services and indicates immediate procurement needs, not forecasted demand.
Therefore, the correct answers areA. Planned orderandD. Planned independent requirement.
For more information, refer to SAP's documentation on differentiating between planning sources in ERP systems: