Question #: 48
Topic #: 5

When an opportunity close date is delayed by more than 60 days, the manager and the VP sales must approve the change. How can this requirement be met? Choose 2 answers


A.

Build an approval process that requires unanimous approval from the manager and VP of sales.


B.

Create a workflow rule that checks for close date less that 60 days and add an email alert.


C.

Create a lightning process builder flow that submits the record for an approval process


D.

Build a validation rule that does not allow a user to save the opportunity record.