The business analyst (BA) at Cloud Kicks is deep in planning activities for its Commerce C oud implementation project. The project sponsor asks the team to.. their efforts due to budgetary constraints.
What should the BA do next?
A.
Ask the project sponsor to increase the project budget.
B.
Ask the project manage to re-prioritize .. requirements.
C.
Ask the project sponsor to request additional resources.
When faced with budgetary constraints, re-prioritizing requirements ensures alignment with available resources:
Budget Optimization: Re-prioritizing allows the team to focus on delivering high-value features while deferring less critical requirements.
Role Collaboration: Salesforce recommends close collaboration between the BA and project manager to adjust project scope and maintain alignment with business goals.
Stakeholder Alignment: This approach ensures transparency with stakeholders about changes in project focus due to budgetary constraints.