When the change authority asks for more information regarding a proposed change, this occurs during the 'Assessing issues' step of the 'issue management technique' in PRINCE2. This step involves evaluating the impact and implications of issues or changes, including requesting additional information necessary to make informed decisions.References: PRINCE2® 7 Foundation resources on issue and change management.