PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 132 Topic 14 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 132 Topic 14 Discussion

Prince2-Foundation Exam Topic 14 Question 132 Discussion:
Question #: 132
Topic #: 14

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?


A.

Deciding on changes


B.

Implementing changes


C.

Assessing issues


D.

Capturing issues


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.