PMI PMO Certified Professional PMO-CP Question # 22 Topic 3 Discussion

PMI PMO Certified Professional PMO-CP Question # 22 Topic 3 Discussion

PMO-CP Exam Topic 3 Question 22 Discussion:
Question #: 22
Topic #: 3

How many performance indicators should be used for each PMO function in each evaluation cycle?


A.

Only key functions should be monitored with performance Indicators, reducing bureaucracy and excessive control.


B.

One indicator per function, giving focus to what really matters.


C.

From two to four indicators, allowing the benefit of controlling to be compatible with the effort to achieve it.


D.

All the indicators recommended by the methodology.


Get Premium PMO-CP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.