PMI Project Management Office Certified Professional PMI-PMOCP Question # 34 Topic 4 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 34 Topic 4 Discussion

PMI-PMOCP Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

An established PMO has a forecast of the expected benefits from all current and planned initiatives for the next 3 years. Due to a new regulation, the portfolio delivery plan needs to be reviewed to ensure that compliance will be realized by the given due date. The engineering department proposes to delay a strategic initiative to free up some resources for the compliance project.

What should the PMO manager do first?


A.

Assess the impact of the proposed change on the benefits delivery plan.


B.

Propose the change to the portfolio board in order to get the new benefits delivery plan approved.


C.

Give advice to the portfolio board to outsource the compliance project so the benefits delivery plan will not be affected.


D.

Evaluate the portfolio and check how the benefits delivery plan can be optimized.


Get Premium PMI-PMOCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.