PMI Project Management Office Certified Professional PMI-PMOCP Question # 10 Topic 2 Discussion

PMI Project Management Office Certified Professional PMI-PMOCP Question # 10 Topic 2 Discussion

PMI-PMOCP Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

The board of directors wants to oversee the company ' s strategic portfolio of capital projects. The PMO will support the portfolio management.

What should the PMO professional do to ensure that the portfolio ' s alignment to strategy meets the executives ' expectations?


A.

Define the proper portfolio alignment to the company ' s strategy.


B.

Establish a benefits realization process to ensure aligned business outcomes.


C.

Implement a portfolio management software for tracking progress.


D.

Develop a feedback loop so executives can provide their perceptions of service outcomes.