A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?


A.

Meet with the customer and apologize for misunderstanding the business's need.


B.

Suggest re-estimating the requirement and following the change control process.


C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.


D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.