PMI Professional in Business Analysis PMI-PBA Question # 23 Topic 3 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 23 Topic 3 Discussion

PMI-PBA Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

A business analyst is trying to complete the requirement documentation of a project and finds that the developers have started development. The business analyst should first facilitate the:


A.

requirements gathering workshops with the stakeholders.


B.

requirements acceptance with the customer.


C.

requirements validation with the testers.


D.

requirements sign-off with the customer.