Question #: 19
Topic #: 2

In the early stages of an AI project, the team needs to determine the types of environments and devices where the AI solution will be used. This information is crucial to ensure a successful implementation.

Which action should the project manager implement first?


A.

Perform a technical requirements audit.


B.

Hold workshops with end users to gather feedback.


C.

Conduct comprehensive user experience research.


D.

Draft a detailed usage scenario analysis.