PMI Certified Professional in Managing AI PMI-CPMAI Question # 8 Topic 1 Discussion

PMI Certified Professional in Managing AI PMI-CPMAI Question # 8 Topic 1 Discussion

PMI-CPMAI Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

An IT services company is integrating an AI solution to automate its customer service functions. The integration team is facing resistance from the customer ' s employees.

Which action should the project manager perform to manage this risk?


A.

Conduct all-hands meetings on the benefits


B.

Offer the option to join another team


C.

Implement a gradual phased rollout


D.

Mandate immediate transition from management